Meta Hyperion

Meta is developing Hyperion as a major internal AI training cluster. The capacity cited here is a future design target.

Meta Hyperion is an under-construction GPU cluster run by Meta in Richland Parish, Louisiana, United States. Planned power: 5,000 MW.

Big tech

Verified

Operator page Compare with others Request GPU capacity

Facts

Source per value
Owner / operator Organization that owns or operates the GPUs. Hosting and facility roles are listed under Partners.
Meta 1
GPUs installed Physical GPUs in the cluster, from the operator or a deterministic sum of disclosed quantities (nodes × GPUs per node). Planned counts, H100-equivalents and unaudited press totals are never counted here.
Not published
Location City, region and country where the cluster sits. Empty when the operator does not name the site.
Richland Parish, Louisiana, United States 2
Country Country of the cluster, taken from the location.
United States 2
Live power MW Power in service, in megawatts of IT load where the source says so. Company figures are marked in the notes; Epoch AI satellite estimates are labelled as estimates.
Not published
Planned power MW Planned or contracted power at full build, in megawatts.
5,000 1
Power notes Basis and date of the power figures, and who published them.
Meta’s site page cites 5 GW of compute capacity at full build; a Meta spokesperson said 2 GW by 2030. 1
Status operational = running and named as such by the operator or a primary source; partly operational = a phase is live and more is coming; under construction = building underway; announced = disclosed or contracted with no confirmed go-live.
under construction 1
Operational since Month or year the source gives for the cluster going live (first phase for partly operational clusters). Empty when no date is published.
2028 1
Status notes The source’s wording on status, with the date.
Announced future cluster; the 5 GW figure is a design target. 1

Sources

  1. engineering.fb.com accessed 2026-11-11
  2. engineering.fb.com accessed 2026-11-11
  3. Meta data centers: Richland Parish accessed 2026-11-11

Related clusters

All 87 clusters

Lists

Need GPU capacity at this scale? Request quotes from GPU cloud providers

Tell us what you need once. We send it to matching GPU cloud providers and they reply to you directly.

Quote requests open shortly. To get in first, email hello@gpuclusterlist.com.