Lambda Kansas City AI Factory
Lambda announced a dedicated supercomputer for one customer’s large-scale AI training and inference.
Lambda Kansas City AI Factory is an announced GPU cluster run by Lambda in Kansas City, Missouri, United States. It runs NVIDIA Blackwell Ultra; no installed GPU count is published. Planned power: 100 MW.
Facts
Source per value- Owner / operator Organization that owns or operates the GPUs. Hosting and facility roles are listed under Partners.
- Lambda 1
- GPU maker NVIDIA, AMD or Intel, taken from the GPU model.
- NVIDIA 1
- GPU model Accelerator model or family as disclosed. A GH200 is one GPU on a superchip; an MI300A is an APU that contains a GPU.
- NVIDIA Blackwell Ultra 1
- GPUs installed Physical GPUs in the cluster, from the operator or a deterministic sum of disclosed quantities (nodes × GPUs per node). Planned counts, H100-equivalents and unaudited press totals are never counted here.
- Not published
- GPU count notes What the count covers (one partition, one site, a design limit), qualifiers and competing figures.
- More than 10,000 initially. 1
- Location City, region and country where the cluster sits. Empty when the operator does not name the site.
- Kansas City, Missouri, United States 1
- Country Country of the cluster, taken from the location.
- United States 1
- Live power MW Power in service, in megawatts of IT load where the source says so. Company figures are marked in the notes; Epoch AI satellite estimates are labelled as estimates.
- Not published
- Planned power MW Planned or contracted power at full build, in megawatts.
- 100 1
- Power notes Basis and date of the power figures, and who published them.
- 24 MW initial, more than 100 MW potential (Lambda, October 2025). 1
- Status operational = running and named as such by the operator or a primary source; partly operational = a phase is live and more is coming; under construction = building underway; announced = disclosed or contracted with no confirmed go-live.
- announced 1
- Status notes The source’s wording on status, with the date.
- Announced October 2025 for an early 2026 launch; no go-live confirmed as of 9 Nov 2026. 1
Sources
- lambda.com accessed 2026-11-11
Related clusters